Will Warner Road connect through to Power Road? Mesa’s public records show a planned bridge connection in the Power-to-Sossaman corridor, and the city has taken the concrete step of seeking professional design services. The records reviewed for this story do not establish when drivers will be able to use it. City of Mesa. City of Mesa.

The project in the public record

Mesa’s engineering opportunities page lists CP1330BRDG Warner Road Bridge, with a response deadline of October 15, 2026, at 2 p.m. The page explicitly identifies these opportunities as professional design services. City of Mesa.

That distinction matters. A request for design qualifications is a step toward working out a project. It is not a notice that construction has begun, and the response deadline is not an opening date.

The city’s Transportation Master Plan also identifies a new crossing over the Roosevelt Water Conservation District canal and East Maricopa Floodway along Warner Road between Power and Sossaman roads. Those are the obstacles the planned connection must cross. City of Mesa.

What the connection would change

The purpose is to link this part of Warner across the canal and floodway. For anyone trying to understand the proposal, the clearest picture is a map with Power Road on one side, Sossaman Road on the other and the Warner alignment between them.

It is too early to turn that map into a promise about minutes saved on a commute. Travel times would depend on the final design, traffic patterns and the roads feeding the connection. The documents cited here do not support a specific time-saving claim.

What we know about timing

The October design deadline is a dated milestone that can be verified. A construction start, contractor award and opening day have not been verified for this story. A planning document’s broad time horizon should not be presented as a committed construction schedule.

The next useful records to watch are a design selection or contract, an updated project schedule and a construction award. Those would help show how far the proposal has moved beyond planning and procurement.

For now, the answer is that Mesa has documented the Warner connection and sought design services for its bridge project. The answer to when you can drive it still needs a confirmed schedule.

What Mesa’s capital plan budgets

Mesa’s adopted FY2027–2031 capital improvement plan lists $37,883,980, or about $37.9 million, for CP1330, Warner Rd Bridge. The project sheet is printed page 273 (PDF page 285).

The plan assigns $3,153,400 to design in FY2026–27, $34,082,598 to construction in FY2027–28, and $647,982 to administration. Its funding columns list $16,847,534 from the 2026 Street Bond and $21,036,446 from the Local Streets Fund.

This is an adopted planning budget, not a final construction bid or proof that every funding step is complete. The spending years are planning years; they do not establish a construction award, start date or opening day.