Drive west on Vaughn Avenue past Ash Street in downtown Gilbert and the pavement ends in a circle beside the Union Pacific tracks. Today, that’s where you turn around. Gilbert is building a road from that turnaround to Neely Street, giving people another way into the Heritage District from Guadalupe Road.

The Vaughn Avenue Connector also has a job on the other side of the railroad. Gilbert is moving a stormwater basin there so it can collect more runoff when heavy rain hits downtown.

How the route will work from Guadalupe Road

Once the connector opens, you’ll be able to turn south from Guadalupe onto Neely, follow the new road southeast along the east side of the tracks, then head east on Vaughn past Ash and into downtown. The bend keeps the road on the same side of the railroad the whole way. Gilbert plans a low-speed street on the approach to the shops and restaurants in the district.

For people walking or biking, one of the biggest changes will be on Neely itself. The plans call for a 14-foot-wide shared path along the east side of the existing street, with landscaping and new lighting. The roadway will shift west and remain two-way, with some curbside parking on the west side. Gilbert’s project FAQ includes the street and path plans.

The new entrance is taking shape as private development adds homes and commercial space in the district, including Heritage Park. ABC15 covered the two projects at the connector groundbreaking.

Why crews are moving earth across the tracks

Gilbert says the existing basin beside the railroad struggled to keep up during some of the area’s heavier storms. The town chose a site on the south side of the tracks where the new basin can hold more water. Gilbert described the drainage work at the September 9 groundbreaking.

Curved terraces of graded earth and construction equipment south of the railroad tracks near Vaughn Avenue.
Grading south of the Union Pacific tracks on November 17, 2026. Gilbert plans to relocate its stormwater basin to this side of the railroad. Still from East Valley Explorer footage.

When it will open and how to reach businesses during construction

Gilbert expects to finish in 2027. Its November Heritage District update lists summer, while the engineering project page lists winter. The town has yet to announce a day when the new road will open to traffic.

Utility work began at Guadalupe and Neely. The town’s construction plan takes crews south on Neely, then east toward Vaughn. Businesses along Neely are to keep driveway access during the work. Where a business has just one driveway, crews plan to rebuild one half at a time. The university building on Vaughn is also expected to remain accessible. For questions about reaching a particular property, the project hotline is 480-898-4090.

How Gilbert is paying for the work

Gilbert’s transportation bond overview lists a $57.47 million budget for the road project, with 85% funded by the voter-approved bond. The same table lists the Vaughn Basin Relocation separately, with a budget of $17.15 million.

For another look at how people will get around Gilbert, read our guide to the new Ocotillo Road bridge.